5 active job(s) · cost-to-cost actual margin · drillable to cost code (§102)
§ 151Job profitability
CONTRACT VALUE
$2,516,550.00
COST TO DATE
$1,219,350.00
EARNED MARGIN
$278,786.04
11.1% blended
Per-job
| JOB | CUSTOMER | CONTRACT | EST COST | COST TO DATE | REVENUE EARNED | MARGIN | FORECAST AC MARGIN |
|---|---|---|---|---|---|---|---|
| JOB-26-101Cedar Bluff Ridge - new build | Cardinal Ridge Wireless | $1,295,000.00 | $985,000.00 | $443,900.00 | $583,656.50 | $139,756.5023.9% | $310,000.00 |
| JOB-26-102Hollow Creek - tower modification | Summit Line Networks | $480,000.00 | $372,000.00 | $289,400.00 | $373,440.00 | $84,040.0022.5% | $108,000.00 |
| JOB-26-104Manzanita Pass - 4-site decommission | Northgate Tower Group | $311,600.00 | $259,500.00 | $231,750.00 | $278,289.96 | $46,539.9616.7% | $52,100.00 |
| JOB-26-103Elkhorn Flats - carrier add | Blue Heron Telecom | $278,250.00 | $214,000.00 | $85,400.00 | $111,049.58 | $25,649.5823.1% | $64,250.00 |
| JOB-26-105Silver Fork - generator & civil | Larkspur Broadband | $151,700.00 | $117,500.00 | $168,900.00 | $151,700.00 | -$17,200.00-11.3% | -$17,200.00 |