Loading this screen…
| Job | Contract | Est. cost | Cost to date | % compl. | Earned | Billed | Billed vs earned | Over/(under) | Budgeted margin |
|---|---|---|---|---|---|---|---|---|---|
| JOB-26-101 Cedar Bluff Ridge - new buildCardinal Ridge Wireless | $1,295,000.00 | $985,000.00 | $425,500.00 | 43.2% | $559,440.00 | $0.00 | ($559,440.00) | 23.9% | |
| JOB-26-102 Hollow Creek - tower modificationSummit Line Networks | $480,000.00 | $372,000.00 | $128,300.00 | 34.5% | $165,552.00 | $0.00 | ($165,552.00) | 22.5% | |
| JOB-26-104 Manzanita Pass - 4-site decommissionNorthgate Tower Group | $311,600.00 | $259,500.00 | $53,350.00 | 20.6% | $64,064.96 | $0.00 | ($64,064.96) | 16.7% | |
| JOB-26-103 Elkhorn Flats - carrier addBlue Heron Telecom | $278,250.00 | $214,000.00 | $54,200.00 | 25.3% | $70,480.73 | $0.00 | ($70,480.73) | 23.1% | |
| JOB-26-105 Silver Fork - generator & civilLarkspur Broadband | $151,700.00 | $117,500.00 | $46,100.00 | 39.2% | $59,511.91 | $0.00 | ($59,511.91) | 22.5% | |
| 5 active jobs | $2,516,550.00 | $1,948,000.00 | $707,450.00 | 36.3% | $919,049.60 | $0.00 | ($919,049.60) | 22.6% |